Correction: the pushed tip is db9e59b4.
Plan 6b: 24 hours without a merge (stopping rule 8), and a switch-on date (rule 5) Question closed
On branch plans-6b-checkout-flow
Stopping rule 8 report, 2026-10-27 10:30 UTC. Plan 6b started 2026-10-26 about 09:48 UTC; nothing has merged since 6a.
Where it stands:
- Tasks 0 to 12 and 14 are built, reviewed and pushed (tip 5a…, see the branch). Task 13 (the account-deletion retirement gate) is building now. Task 15 (Luna copy pass, docs, census, gates) is next, then the merge of main, the census re-layer, one whole-branch Astra review and the copy review with Paul.
- Nothing is blocked. The time went on per-task review rounds, which rule 3 allows for billing, and one overnight usage-limit stop.
The last two review rounds per task, briefly:
- Task 10: one P1 (an upgrade checked current items rather than still-paid packs) and a plan-level P1: a billing problem opened by the request's own read did not stop a charge. Ruled: charging flows re-check problems after their reads, through one helper; renewal stop and resume are exempt. Re-review clean.
- Task 11: two P1s (an unknown historical price recorded as 0 authorised a charge; a failed database read reported a successful join). Both fixed; re-review clean.
- Tasks 12 and 14: approved first round, no P1.
- No task hit rule 2 (two rounds in one fault family). Task 8 came closest: two rounds on "the submitted currency must match the prices shown", ended by a structural fix (every sold currency's prices rendered, CSS shows the checked one).
Cut I recommend: none needed yet. If the whole-branch review finds a P1 in round 1, I would cut team seats (Task 11) to a follow-up branch rather than run more rounds, since that is where most of the risk sits.
Question for Paul (rule 5): 6a, 6b and the pricing page have no switch-on date. When should they switch on? I'll ask before asking to merge.
Rule 5 answered by Paul (2026-10-27): "as long as existing users don't have to start paying, happy to switch on when ready." Recorded as: 6a, 6b and the pricing page switch on after 6c (Paul's live Stripe setup and dev rehearsal) and the live catalog change in carloku-infrastructure. Before the catalog goes live, every existing account is sponsored at its current usage (carlos accounts plan --set free --sponsored limits.json --reason "existing account"); billing never touches an operator-set or sponsored plan. Copy review: Paul approved all strings. Remaining: apply the copy, green CI, Paul's merge.
Merged as bf55f29e (squash of b44ac84d, tree identical) on Paul's go, 2026-10-27 14:13 UTC. CI green at b44ac84d. Dormant until 6c; switch-on after 6c with existing accounts sponsored first. Follow-ups in docs/superpowers/notes/plans-6b-followups.md.